Project Overview
This project will perform necessary maintenance to improve the riding/walking surface of the Charlotte and Curtis Ward Bike Trail by performing spot repairs and resurfacing, and will be performed in collaboration with Department of Conservation Natural Resources. The trail was initially constructed in 2000.
Charlotte and Curtis Ward Bicycle Trail resurfacing begins May 26
Status
- Design
- Bid Advertisement
- Contracts
- Construction
Development of final punch list is underway. All construction work complete other than striping, including sealcoating of the Wrights Mill Road trailhead parking lot.